Supplier information obligations under Article 16

Article 16 is short and is the most load-bearing provision in the documentary chain. It places on suppliers of packaging or packaging materials the obligation to give the manufacturer everything the manufacturer needs to demonstrate conformity — including the technical documentation referred to in Annex VII and the information required under or pursuant to Articles 5 to 11 — in paper or electronic form, in a language the manufacturer can easily understand. Without it, Article 15 is a duty the manufacturer cannot discharge.

1. Who is a supplier, and who is not

The supplier is defined in Article 3(1)(16) as the natural or legal person that supplies packaging or packaging material to a manufacturer. The category covers converters, printers, board and film producers, and component makers. It does not describe the operator whose name goes on the finished packaging: that party is the manufacturer under Article 3(1)(13), even where a contract packer physically produced the item. The distinction matters because a co-packer or converter is a supplier under Article 16, while the brand owner on whose behalf the work was done is the manufacturer under Article 15.

One consequence is worth stating plainly. A brand owner cannot delegate the Article 15 duty to its packaging supplier, and cannot treat the supplier's own declaration as its own. What it can and must do is obtain the supplier's information and hold it in its own file.

2. What the supplier owes

Article 16 is expressed as an outcome rather than a list: the supplier provides all the information and documentation necessary to demonstrate conformity. In practice the outcome resolves into the data points below, because each of them is needed for a specific requirement that the manufacturer has to evidence. The list is functional, derived from Articles 5 to 11 and Annex VII, not a verbatim schedule.

Table 1 — Data points the manufacturer needs from the supplier, and the requirement each evidences
Data point What it must contain Requirement evidenced Weak form to reject
Material composition Material by layer and by component, with grammage and share by weight Annex VII · Art. 6 "Paper-based" with no layers or weights
Packaging weight and dimensions Nominal weight per unit, and the dimensions of the component as supplied Art. 10 · Annex IV Weight of the finished pack only
Heavy metals Measured Pb, Cd, Hg and Cr(VI) in mg/kg, per component, with method and sample reference Art. 5(4) "Complies with 94/62/EC" with no values
PFAS, where food contact Targeted PFAS results in ppb and total organic fluorine in ppm, with method Art. 5(5) "PFAS-free" as an assertion
Substances of concern Identification of substances of concern in the material and components, and how they were minimised Art. 5(1) No response at all
Recycled content Share of recycled content in plastic components, with verification route Art. 7(1) A percentage without a verification basis
Recyclability data Material and design data relevant to the applicable performance grade Art. 6(3) A general claim of recyclability
Standards and specifications applied Harmonised standards or internal specifications relied on, with versions Annex VII · Annex IV Standard cited without a year or edition
Traceability Batch identification allowing a delivered component to be linked to a declaration Art. 15(5) · Art. 22 No batch marking on the delivered goods
Labelling data Material composition data sufficient to support the Article 12 label where applicable Art. 12 Label applied without underlying composition data

3. The language and form requirement

Article 16 requires the information in one or more languages the manufacturer can easily understand, in paper or electronic form. Both elements are operative rather than decorative. A data pack delivered only in a language the manufacturer's compliance function cannot read is not a compliant delivery in substance, even if it was delivered. And the electronic route is what makes the ten-day production window of Article 15(10) achievable: a supplier that holds the data but needs three weeks to retrieve it converts into a manufacturer's failure.

4. Article 16 does not stop at the first tier

A converter that buys board from a mill and film from a producer is a supplier to the manufacturer, but is itself dependent on its own upstream suppliers for the composition and substance data. The Regulation does not impose Article 16 directly on the mill in that chain unless the mill also supplies a manufacturer, but the practical effect is a chain of requests: the manufacturer asks the converter, the converter asks the mill, and the data arrives or does not. Files fail at the deepest point of that chain, and they fail quietly.

The working response is to make the request specific and dated at the point of purchase order, rather than generic and retrospective at the point of audit. The template below is built for that purpose.

5. Copyable supplier information request

The template covers the data points in Table 1. It is drafted as a request to a supplier under Article 16 and is deliberately explicit about what will be rejected as insufficient. Copy it, complete the bracketed fields, and attach it to the purchase order rather than sending it after delivery.

Article 16 Supplier Information Request Editable template · copy as plain text

Complete the four fields. The request appears here.

Template only. Article 16 of Regulation (EU) 2025/40. Adapt the wording to your contractual and language context before sending.

6. What to do when the supplier cannot answer

A supplier that cannot provide measured values leaves the manufacturer with a choice between substituting its own testing, changing supplier, or holding a gap it can document and explain. The third option is the one that is often taken silently, and it is the one that fails under examination, because a file that does not contain the data does not contain an explanation either. If a data point is genuinely unavailable, the defensible course is to record the absence, the reason, the mitigation and the date by which it will be closed — in the file, not in an email thread.